We left the deck furniture out because we thought we would be able to put it in the garage in early December. Clearly not a good assumption.
Schdule:
- trim: 3-5 wks (overlaps with drywall)
- paint: 1 wk
- flooring: 1 wk
- cabinets: 1/2 wk
= final painting: 1 wk
Total: 7 - 9 wks - end of February