There is a time for everything. And this relates to building a house.
The drywall completion is the activity that is currently pushing the schedule. The drywall taping and mudding must be completed before the trim out can start. And the trimming must be virtually completed before the painting can start. I spoke to two painters this evening, and they both said it would take a week to paint the house. I am meeting another painter at the house tomorrow after work.
Doesn't seem likely that the floor installation can start next Wednesday. Which possibly means that the cabinetry not arriving until Jan 30th is not pushing the schedule either.