Things to do so drywall can start on Thursday:
1. Vapour Barrier inspection - Charles will call on Monday morning.
2. Complete strapping installation.
3. Complete framing around fireplace.
4. Complete framing around shower in master bath, includes wood jamb for edge of door and shower base.
5. Complete shower base for Tawny washing area in the laundry room.
6. Complete central vac rough-in.
6. Complete electrical work: A few things left to do: move the pantry light from a wall where the fixture won't fit to above the door where it should have been, lower the box for a closet light that was installed before the closet ceiling was dropped to 8', and move a 120V wire that was run through the same hole in the floor as the networking -- a major no-no.
7. Complete plumbing rough-in. I thought this was supposed to have been done a week and a half ago.
Supplies:
We ordered the trim supplies last week. They should be delivered towards the end of this week.
Flooring supplier has missed what seems like his 4th or 5th appointment to take measurements. We are concerned about getting the materials in time and therefore causing a delay. However, Mike called us on Friday to say that all the products we want are stock items with his suppliers and there should be no problems getting it in for us.