Monday Dec 19th, 2005
Everyone is driving for the drywall. The plan is to be ready to start drywalling on Thursday, so the punch list of things to complete for then is steadily shrinking.
One thing that wasn't on the punch list but was on the annoyance list - was the wrong chimney cap is replaced. The fireplace people came and straightened out the pipe supports and installed the correct cap.
This is Chris tacking up furring strips. They will need to fastened in properly for the air test and also for the the insulation. The insulation guy should be ready to roll with the insulation on Wednesday.
electrician and plumber discussing some topic in the laundry room.
Andre - got the heat going
Nick - wiring basement, moved boxes that were at the wrong height above the desk
Plumber finishing up rough drywall
Buchan, Lawton, and Peron - scheduled for air test
Called in request for electrical inspection on main floor
Things to do: Go over central vac locations, review partitions with sound insulation
Call Thorston to schedule attic insulation.