This is Dave's and Charles' plan (from about a week ago) to complete our house for the end of January.
Week of: Description
Week 1 (Nov 28): Electrical, plumbing, central vac rough in, interior framing. Tubs and toilet delivered.
Week 2 (Dec 5): Complete electrical, plumbing rough in. Poly and strapping.
Week 3 (Dec 12): Strapping, drywall, insulation.
Week 4 (Dec 19): draywall, mud, sanding, priming / prime check.
Dec 26: no plans - catch up.
Week 5 (Jan 2/06): Mud, levelling, flooring
Week 6 (Jan 9): Doors, painting, cabinets
Week 7 (Jan 16): Trim, Electrical, plumbing finishing.
So... lots of time!!!
In other action... another drywaller and painter came to measure and give us a quote. Also a guy who does railings came to give a quote for the stairs to the basement.