Friday, May 27, 2005

Day 51 - squaring, truing, and leveling....


Progress to week ending May 27th was a bit slower this week as Chris was sick for 3 days, and of course Monday was a holiday (Victoria Day).

Most of the walls are squared. Next week the crew will finish squaring, truing, and leveling. Kickers will be installed on the corners (to hold the walls in square), and the bottom edges of the blocks will be foamed to fill any gaps and glue the blocks to the footings.


The new crew members: Brian & Steve

The new crew members who joined us this week: Brian Breton and Steve Molson.

Brian has signed on for the ICF portion of the construction. Steve is signed up for the full meal deal. As you can see from the rust stains on Steve's attire, he's been working hard shifting rebar on the job site.

No comments: