Charles, our builder, talked with us about ordering the trusses. The plan, assuming no further weather delays, is as follows:
Week starting: Plan
May 2nd (day 26) - complete and pour footings
May 9th (day 33) - start on basement ICF walls (1.5 weeks)
May 20th (day 44) - basement walls complete, start to install main floor (1 wk)
May 27th (day 51) - main floor complete (includes plumbing & electrical rough-in), start to install main floor ICF walls
June 7th (day 62) - main floor ICF walls complete
June 14th (day 69) - trusses installation complete.
Now to figure out when the house will be closed in so we can have a good idea on when we can put our current house up for sale.
Did I mention that it rained again today? Figures...