Time to look at the plan that we talked about on Day 26 - Looking ahead....
Update on major components...
main floor joists - ordered.
trusses - not ordered yet. smart move, due to schedule slip.
windows - reviewing the sizes, etc, this evening. Order should be placed tomorrow.
We had difficulties with the concrete mix for the footings, so that in conjunction with the weather(!!) caused just over a week's delay. So here is the updated plan, with a 9 day schedule slip.. We also have a few days delay as the next delivery date for the ICF blocks is Tuesday, May 24th... (schedule updated again below)
Week starting:
May 24th (day 48), new: ICF blocks delivered
May 24th (day 48); was May 9th (day 33): start on basement ICF walls (1.5 weeks)
June 2nd (day 57); was May 20th (day 44): basement walls complete, start to install main floor (1 wk)
June 9th (day 64); was May 27th (day 51): main floor complete (includes plumbing & electrical rough-in), start to install main floor ICF walls
June 21st (day 76); was June 7th (day 62): main floor ICF walls complete
June 28th (day 83); was June 14th (day 69): trusses installation complete.