Nov 4 - Complete roof framing (including sheeting, gables, roof ribbons, strapping, returns)
Nov 11 - Complete framing interior
Nov 18 - Complete garage floor (est 3 days work, but allow 2 days for delays due to assisting other trades), and garage stairs (garage to laundry room, and garage to basement stairs).
Dec 2 - Ready to drywall. Call cabinet maker to take final measurements for kitchen, bathrooms, and laundry.
Dec 16 - drywall boarding complete (2 weeks). Have trim here.
Then comes...
flooring, cabinets, trimming, finish electrical, plumbing, HVAC.
Phew! There's a lot of work still to go, but there is time to make it happen.
Exterior Colours
We spent 4-5 hours yesterday (Sat) driving around looking at shingle colours. We had decided that our original selection (blog entry Oct 8th) of IKO Renaissance XL in Weathered Slate is what we want. We were distracted by the sample which appears very grey. Charles suggested that the dark brown colour for the metal valleys would go well with the shingles, so we are going to use that also.

Powder room quandry

So we now need to return the tall Fairfax faucet (and pay a 15% restocking fee) and order the correct faucet. The silver lining in this cloud is that we found a sink that we like even better (Kohler Serif - K2075-1) which is a little bit cheaper. At least that will take the edge of HD's restocking fee...