Thursday, February 03, 2011

Finish electrical and flooring lay down.


Today I installed the breakers in the panel, and most of the finish electrical. This photo shows that:
  • the lights were on a new circuit that is now energized
  • the lights/plugs have the Decora wall plates on them
  • Trimmed flooring to fit kitchen (not installed yet)
We are moving in on Saturday. What's happening to enable that:
  • Kitchen cabinets are being delivered on Friday morning and installed starting on Friday afternoon.
  • Kitchen appliances are being delivered on Saturday.
  • The bathroom floor has been grouted, as has the ensuite shower walls and most of the main bath walls (I didn't have the right grout for the main bath walls so have to get that this morning).
  • Still have to fill and sand the screw holes in the kitchen so the flooring can be laid down - must be done today so the cabinets can go in on Friday.
  • Still have to paint the bathrooms so the finish plumbing can be done on Friday afternoon.

Tuesday, February 01, 2011

Yeoman service - last night for old furnace


This is the kitchen floor. I had planned to install the new flooring (it's the long tube rolled up by the vacuum cleaner), but we couldn't get the old floor off cleanly. Since so much of the flooring was just lifting off, I thought it would all lift off, but no such luck. I ended up taking off the old subflooring (3/8" plywood) and will replace it and screw it down properly, so hopefully there are no squeaks.

This is our old furnace. It is the last night for the old lady because the new gas furnace goes in tomorrow.

Good timing too, as the oil tank is almost empty! (It's below E on the gauge!)

Monday, January 31, 2011

last day of January


Unpacked vanity for main bath so we could see where the baseboard needs to stop.

The new baseboard is a vast improvement over the old. The house is a mess now - please excuse that.

See the baseboard in the main bath? It stopps where the vanity starts.

Also put up drywall in the laundry room. Still have to complete screwing it in, cut out the window opening and tape and mud. Oh yes, prime and paint it too - before Thursday!

Priming


Another 13 hour day. Sanding, Cleaning up. Priming. Durabond 90. Cleaning tools. Sanding. Cleaning up. Prime check... Kitchen and bathrooms.

Friday, January 28, 2011

Gas hookup


Thursday: the guys from Aecon came to see what they had to do to hook up our natural gas line. They then left the backhoe in the driveway and a trailer-mounted compressor on the road and went home.

The digging started early, guessing that it was around 8am as that's when the breaker tripped when they broke the electrical wire to the post light.

Working away, doing who knows what.

And now we have a gas meter on our house, ready to be connected to a furnace. The furnace is supposed to come on Wednesday.

PS: Yes, they fixed the electrical wire to the post light.

Inside the house on Thursday and Friday


On Thursday, Mario and his crew finished installing the doors upstairs and doing the trim out. I think the doors look really sharp, and Mario did a good job with the trim in such a tight space.

On Friday, Louis was mudding all day (drywall) and I was doing running around, getting things, making phone calls, cleaning up, and then cleaning the tile in the ensuite in preparation for the grout. I thought the shower looked pretty good before, but it looks even better after being cleaned up.

Oh yes, a guy from Rossen Glass & Mirror came to take measurements for the shower enclosure.

This is what the floor looks like after it was cleaned up.

When I was cleaning the shower tiles, I accidentally knocked over my bucket of water and a lot of water poured down the drain, which is not connected! So that made a mess in the basement for me to clean up.

Thursday, January 27, 2011

Jan 26.4: getting rid of annoyances

Wow - today was a busy day! with lots of stuff accomplished! It seems to me that I spent a lot of time on the phone ordering our main bath and kitchen faucet and accessories (towel bar, etc), as well as confirming that our natural gas hookup will happen by Jan 31st. That will be good because then we can get our new furnace and new tankless water heater installed.

Besides constantly cleaning up, I did manage to get a few things accomplished.

The eco energy audit identified that there was a big draft coming from beside the fireplace. Mario's guys took off the trim so I could caulk it. There were some quite big gaps so I filled it with backer rod (foam gap filler) and then caulked it. I needed to wait for the caulk to set up so I could go back and fill some more. There is over a tube of caulk in this gap!!

Another annoyance was that the stairs from the main level to the bedroom level squeaked. This is my attempt to fix that. I fastened a 2x4 in place under the stair that squeaked the most. The squeaking is because of wood rubbing on wood or wood rubbing on a nail. The risers were nailed to the back of the treads with three nails. When someone walked on the stairs it was obvious that the risers were moving and the squeak was coming from the nails. I glued and screwed this 2x4 to the riser, and the then screwed a few screws from the front (the riser) to help hold it in place. I also put 8-10 screws in to the bottom of the riser (from the back) into the back of the tread, and then removed the three nails that were causing the squeaks.

I had put a number of boxes of floor tile on top of the stair tread that squeaks to simulate the weight of someone walked on the stairs. I will remove the tiles tomorrow and see if the stairs still squeak or if they are okay.

Wednesday, January 26, 2011

Jan 26.3: Tiling the main bath and ensuite walls


Since he couldn't get into the main bath or ensuite because of the insulation guys and the carpenters, Louis decided to lay out the tile for the main bath on the kitchen floor. Not a bad idea as nobody was working in that space.

This is after most of the walls in the main bath tub was tiled.

A closeup of the random glass/marble mosaic. It looks really sharp! All kudos go to Freda for picking out the tile and accent materials.

This is the ensuite shower. Again we have a band of glass tile/marble accent pieces.

And this is a closeup of the accent tile - it is little squares. The tiles have a bit of a striation on them.

Jan 26.2: More doors and trim


As you know, we had the drafty old windows replaced, and at the time I asked the boss if he would be interested in installing some doors and trim for us. He said yes, because he is not as busy in January as a lot of people don't like getting their windows and doors replaced in the cold weather. This is Nick, and he's a whiz with the caulk, patching the nail holes and caulking around the trim.

This is Mike, and he's cutting back the old baseboard as the new casing for the door is wider than the old stuff that we removed.

This photo shows Mario (the boss) at the bottom of the photo and Nick installing the new casing around the old windows. We replaced all the windows except for two - this big picture window in the living room and the big picture window in the dining room. They actually were in pretty good shape and there were no operators in the living room, and two small awning style windows in the dining room.

BONUS PHOTO: Removing the old baseboard unveils the original wall colour! (or one of the original wall colours). Wow.

Jan 26.1: Insulation day


The insulation guys came today. They were supposed to come on Tuesday, but it was so cold on Monday that the truck didn't start so they shifted all the jobs back by one day.

The front door was open while the hose was running up to the attic.

The hallway was really really cramped and crowded. Did I mention that the carpenter and his crew arrived at the same time to install doors and trim?? And of course we wanted to start doing the tile in the bathrooms!

This is afterwards. The insulation is sloped towards the edge of the roof, and there is almost 2' of insulation at the center.

In a couple of places they were able to put some attic vents in place.

The final step is putting the fiberglass insulated attic hatch in place.