Speaking of numbers... 193 tonnes of gravel delivered and placed today...
Pictures tomorrow.
This is a house blog once again. It is also an occasional dog blog, flower blog, and bird or other creatures blog...
Thursday, May 12, 2005
Wednesday, May 11, 2005
Day 35 - concrete stories...
Charles called the concrete company about the speed at which the concrete set up. Others had complained also, as well as their own guys. Charles has never seen such rapid set up, which was at least partially due to the heat.
The concrete company is now adding retarder to the mix to give more open time.
Perhaps they should pay the cost of cleaning up our footings too!
PS: Discovered that sugar can be used as a retarder for concrete. But too much can turn it into an accelerant. Pretty nifty.
The concrete company is now adding retarder to the mix to give more open time.
Perhaps they should pay the cost of cleaning up our footings too!
PS: Discovered that sugar can be used as a retarder for concrete. But too much can turn it into an accelerant. Pretty nifty.
Monday, May 09, 2005
Day 33 - Pouring the footings
Friday, May 06, 2005
Day 30 - footings are ready for concrete

Day 30 - Friday May 6, 2005 - Day 30 - the footings are ready for concrete!
In this photo, you can see the fastbag has been installed. Fastbag is an environmentally friendly way of making footings. #1 - it holds the concrete with less lumber than required by typical form construction. #2 - there is no leakage (waste) of concrete with the bag. #3 - helps prevent "rising damp". (Rising Damp -- sure sounds like a British expression to me...)
Other things to note from this photo...
- You can see the footings are placed directly on the bedrock. You can't get a better foundation than that!
- Note how the footings are stepped to follow the contour of the bedrock. This will save on the concrete required for the footings. You can see the plywood at the end of the upper level of the form where it steps down (left foreground). The basement floor will, of course, be flat. It will be about 4" above the form level by the basement stairs - rectangle at center of photo is the frame for the stairs to the basement from the garage.
- The three black squares in the centre back of the photo are the support posts pads. These transfer the load from the beam that runs down the center of the house to the footings.
A lot of care was taken to level the footings and get the measurements and placement of the footings correct. An absolute level base is required to install ICF walls, otherwise there will be trouble later with concrete blowouts when pouring the walls.
Thursday, May 05, 2005
Day 29 - levelling of footings completed
Tuesday, May 03, 2005
Monday, May 02, 2005
Day 26 - Looking ahead...
Charles, our builder, talked with us about ordering the trusses. The plan, assuming no further weather delays, is as follows:
Week starting: Plan
May 2nd (day 26) - complete and pour footings
May 9th (day 33) - start on basement ICF walls (1.5 weeks)
May 20th (day 44) - basement walls complete, start to install main floor (1 wk)
May 27th (day 51) - main floor complete (includes plumbing & electrical rough-in), start to install main floor ICF walls
June 7th (day 62) - main floor ICF walls complete
June 14th (day 69) - trusses installation complete.
Now to figure out when the house will be closed in so we can have a good idea on when we can put our current house up for sale.
Did I mention that it rained again today? Figures...
Week starting: Plan
May 2nd (day 26) - complete and pour footings
May 9th (day 33) - start on basement ICF walls (1.5 weeks)
May 20th (day 44) - basement walls complete, start to install main floor (1 wk)
May 27th (day 51) - main floor complete (includes plumbing & electrical rough-in), start to install main floor ICF walls
June 7th (day 62) - main floor ICF walls complete
June 14th (day 69) - trusses installation complete.
Now to figure out when the house will be closed in so we can have a good idea on when we can put our current house up for sale.
Did I mention that it rained again today? Figures...
Saturday, April 30, 2005
Day 23 - Rain rain go away...
Friday, April 29, 2005
Thursday, April 28, 2005
Day 21 - another day, another rain delay
It's rained almost all week. The crew got started laying out the footings on Tuesday, but it's rained since then, so it's hard to make progress when you can't work. That was on top of all the rain last weekend. :^(
On the plus side, we've found a generator at a decent price - Kodiak is a Canadian company that uses Honda engines.
On the plus side, we've found a generator at a decent price - Kodiak is a Canadian company that uses Honda engines.